Reclaims or attempts to reclaim land by hydraulic means shall
ensure that the boundaries of the land to be reclaimed shall be
protected by dykes within the landowner's boundaries as to prevent
spillage of any material onto land outside such boundaries.
Reclaims or attempts to reclaimed land shall ensure that the newly
established land level, after settlement, shall not be less than
three feet above the level of highest seasonal soil water and if,
in the opinion of the Director, any land so reclaimed is below the
level by this paragraph, the person responsible for the reclamation
shall bring up the level in compliance with such directions as shall
be given to him as Director;
Constructs or has under his control, and marina, canal, causeway,
reclaimed land or peninsula shall construct and maintain marina,
canal, causeway, reclaimed land or peninsula with vertical sides
revetted by concrete, wood piling or other method approved ... by
the Director; or
Reclaims land shall make adequate provision for storm drainage
so that rain catchment shall not be channeled onto other land whether
or not such land be swampland.
What Director MRCU requires:
Topographic survey produced by a Registered
Surveyor with spot heights marked on in feet relative to Datum.
Three feet above level of highest seasonal soil water is interpreted
at 4 feet above D.O.S. Datum.
Information regarding plans for revetting
of canals, marinas etc.
Information with regards to provision
of storm drainage (can be carried in consultation with PWD Engineers).